Feasibility study on JCM projects development (energy efficiency, and waste and waste

water) under the Bangkok Master Plan on Climate Change, and study on financial and

other facilitation schemes for introducing low carbon technologies



As of 18th March, 2016

Overseas Environmental Cooperation Center



Contents



I. Summary of Operations ................................................................................................ 1

1. Purpose of Operations ............................................................................................... 1

2. Contents of Feasibility Study ................................................................................... 3

(1) Development of JCM projects in the sector of energy efficiency, waste

management and waste water treatment .......................................................... 3

(2) Identification of candidate to form JCM projects ............................................... 5

3. Overview of the Bangkok Master Plan on Climate Change 2013-2023 ................ 7

(1) Climate Change Policy of the Kingdom of Thailand .......................................... 7

(2) Climate Change Policy of Bangkok Metropolitan Administration (BMA) ....... 7

(3) Overview of the Bangkok Master Plan on Climate Change 2013-2023 ........... 8

II. JCM projects development in the sector of energy saving, waste management and

waste water treatment ........................................................................................... 13

1. Energy saving sector ............................................................................................... 13

(1) Summary of the study ........................................................................................ 13

(2) Schedule of the study ......................................................................................... 13

(3) Elaborating on a plan for applying programme approach for building energy

efficiency and financial scheme for introducing low carbon technologies ..... 16

(4) Elaboration on introducing energy saving code such as CASBEE as eligibility

criteria of JCM methodology ............................................................................. 21

(5) Elaborating on a plan for comprehensive energy saving in industrial park .. 25

2. Waste management sector ...................................................................................... 26

(1) Summary of the study ........................................................................................ 26

(2) Schedule of the study ......................................................................................... 26

(3) Study and elaboration on developing JCM project at waste incineration plant

28

(4) Study on actual situation of landfill site, waste collecting system and

administration/regulations in Thailand. .......................................................... 35

(5) Elaboration on waste management JCM project at residential district of

Royal Thai Air Force .......................................................................................... 36

Page 122

Waste Treatment and Disposal

27

Flow of Waste Treatment and Disposal

HW = Household Waste
HHW = Household Hazardous Waste

Municipal Solid Waste

Sanitary Landfill

Composting plant

(1,100 tons/day)

LFG
50% CH4

Compost

Ash Landfill

Electricity

Infectious Waste

Secured landfill

HW

HHW

HHW

HW

HHW

Sai-Mai

Transfer Station

(2,400 tons/day)

(24%)

Nongkham

Transfer Station

(3,600 tons/day)

(36%)

On-Nuch

Transfer station

(3,100 tons/day)

(11%)

Incinerator

At On-Nuch

Disposal center

LFG
50% CH4

10,000 tons/day

Collect and Dispose by Krungthep

Thanakom Co., Ltd.

HW & HHW

Sanitary Landfill

34 tons/day

On–nut Transfer Station

Page 123

บริเวณเตาเผาติดเช้ือฯ

บริเวณสถานีขนถ่ายมูลฝอย
(Wrapping)

บริเวณอาคารที่
พกัอาศัย (แฟลต)

บริเวณโรงงานฯ Compost
1,000 ตัน/วัน

บริเวณถมดิน
กองขยะเก่า

พืน้ท่ีทัง้หมด 580
ไร่

โครงการเช่ารถขยะ

อาคารท่ีท าการศูนย์ฯ

บริเวณโรงงานก าจัดส่ิง
ปฏิกูล ของ กจข.

บริเวณโรงบ าบัดน ้าเสีย
ส่วนกลาง.

โรงก าจัดขยะก่อสร้างฯ

บริเวณโรงงานฯ Compost 600
ตัน/วัน

บริเวณก่อสร้างโรงงาน MBT

Landused map at On-nuch Transfer Station

Infectious Waste Incineretor

Transfer Station
(Wrapping)

Composting Plant 1,000 tons/day

Area for
future plan

Total Area 580 Rai

โครงการเช่ารถขยะ

Office

Nightsoil Treament Plant
Waste water Treatment

Plant

Concrete Waste Recycling Plant 500 tons/day

Composting Plant
(Underconstruction)
600 tons/day

** 1 Rai = 1,600 M2

1. Composting Plant

Page 244

Thank you!