                            1 The project plan
	1.1 Description and scope
		1.1.1 Background
		1.1.2 The problem
		1.1.3 The solution
		1.1.4 Likely impact
		1.1.5 Project Scope
		1.1.6 Architecture of the system
	1.2 Project tasks
	1.3 Lifecycle model and schedule
		1.4 Resources, methods and skills
2 The project work
	2.1 Literature
		2.1.1 Project management
		2.1.2 Software development
		2.1.3 Java EE and JSF
	2.2 Developing the system
		2.2.1 Increment 1 – Equipment records
		2.2.2 Increment 2 – Recording and keeping track of examinations
	2.3 Legal, social, ethical and professional issues
		2.3.1 Legal issues
		2.3.2 Social issues
		2.3.3 Ethical issues
		2.3.4 Professional issues
3 Review and reflection
	3.1 Review of progress of project work
		3.1.1 Review at TMA01
		3.1.2 Review at TMA02
		3.1.3 Review at completion of Increment 1
		3.1.4 Review at TMA03
		3.1.5 Final review
	3.2. Project management review
		3.2.1 Review of life cycle model
		3.2.2. Review of project schedule
		3.2.3 Review of risk register
		3.2.4 Review of working with tutor
	3.3 Literature, resources and methods review
		3.3.1 Review of literature
		3.3.2 Review of resources
		3.3.3 Review of methods
	3.4 Skills development review
		3.4.1 Technical skills
		3.4.2 Project management skills
		3.4.3 Personal development
References
Software Resources
Bibliography
Appendix 1: Examination report
Appendix 2: Requirements of PPE Management System
	Functional requirements
	Non-functional requirements:
Appendix 3: Project schedules
Appendix 4: System architecture
Appendix 5: Analysis of lifecycle models
Appendix 6: Risk registers
Appendix 7: Assessment of credibility of information sources
Appendix 8: Business rules
Appendix 9: Business processes
Appendix 10: Domain structural model and glossary
Appendix 11: Use case models
Appendix 12: Detailed software functional requirements
	UC1 add item of equipment
Appendix 13: Analysis models
Appendix 14: Design models
Appendix 15: persistence.xml file
Appendix 16: Entities and their tests
Appendix 17: Enterprise JavaBeans and their tests
Appendix 18: Web pages navigation plan
Appendix 19: Web pages and backing beans
Appendix 20: Screenshots of web pages
Appendix 21: Requirements-based testing
	A21.1 Increment 1
		Testing session plan
		Summary of findings
	A21.2 Increment 2
		Testing session plan
		Summary of findings
Appendix 22: Stakeholders impact analysis
Appendix 23: Sample project journal entry
Session 24
Appendix 24: Communication with the tutor
                        
Document Text Contents
Page 2

Andrzej Kurczych TM470 EMA PI: B6142764

Contents

Front Page 1

Contents 2

1 The project plan

1.1 Description and scope 4

1.2 Project tasks 8

1.3 Lifecycle model and schedule 8

1.4 Resources, methods and skills 9

2 The project work

2.1 Literature 11

2.2 Developing the system 14

2.3 Legal, social, ethical and professional issues 26

3 Review and reflection

3.1 Review of current stage of project work 28

3.2 Project management review 31

3.3 Resources and methods review 33

3.4 Skills development review 35

References 37

Software Resources 39

Bibliography 40

Appendix 1: Examination report 41

Appendix 2: Requirements of PPE Management System 42

Appendix 3: Project schedules 45

Appendix 4: System architecture 48

Appendix 5: Analysis of lifecycle models 49

Appendix 6: Risk registers 50

Appendix 7: Assessment of credibility of information sources 52

2

Page 152

13.08.17 A. Kurczych TM470 progress update -

13.08.2017

A progress update on the work completed

and planned.

15.08.17 C. Damm Re: TM470 progress update -

13.08.2017

An acknowledgement of the progress update.

18.08.17 C. Damm Tutorial - Tuesday 28th

August at 19.30 Ref:

164927656

Information about upcoming tutorial with

some advice regarding EMA.

27.08.17 A. Kurczych TM470 progress update -

27.08.2017

A progress update on the work completed

and planned.

29.08.17 C. Damm Re: TM470 progress update -

27.08.2017

An acknowledgement of the progress update.